Continued business growth.

Due to the continued business growth of BNE, the building work has started on the new Barden Network Engineering depot in Dunkeswell. This depot will be used for the BNE Jurassic Fibre contract, and the Jurassic Fibre team hope to move into their new offices in the next few weeks.

Great news for both BNE & Jurassic Fibre team.

Categories
News

Another Milestone Hit

The Jurassic Fibre team successfully hit its target of 10,000 homes by the end of June. JFL’s Construction & OSP Manager, emailed Firstly can I pass on a massive thank you to you and the whole team on behalf of  JFL construction for making June a success’ and JFL’s Director of Network Fibre Construction & OSP, said ‘Great month of June with our latest milestone hit’.

Categories
News

Jurassic Fibre

Jurassic Fibre thank Barden Network Engineering for hitting a major milestone as we have completed a 21km telecoms infrastructure link to Exmouth POP site and have finished the ODF build ahead of the target completion date.